The Web of Dreams
 
Playa Time Line
 
 

-- Day 1 -- August 22 --
Core crew of 12 people arrive on the playa, set up base camp, erect main dome, set up temporary lighting, sound system, and control room for IBVA.

-- Day 2 & 3 -- August 23-24 --
Main support strands are strung and tightened for all levels. Astrological symbol starts to become identifiable from top view.

-- Day 4-6 -- August 25-26 --
We tighten up all support strands and begin cross wrapping.

-- Day 7 -- August 27 --
Second support team arrives on the playa. We continue cross wrapping and start hanging Christmas lights, and start wiring for sound, triggers, and etc. Secondary lights are installed and everything is hooked up and power turned on. The web is expected to be fully functional.

-- Day 8 -- August 28 --
Debugging and finish any loose ends.

-- Day 8-16 -- August 28 - September 4 --
Burning Man

-- Day 17 -- September 5 --
We separate all the lights from the plastic and begin take down phase.

-- Day 18 -- September 6 --
The web should be completely down and organized into loadable sections and loaded.

-- Day 19-21-- September 7-9 --
We Moop our camp and help others Moop their camp.

--Day 22 -- September 10 --
Depart Burning Man and head home.

 
 